Demand Gantt report

This report shows a graphical representation of the complete plan of a certain demand. The plan show all planned activities from raw material purchase orders, distribution orders between locations, manufacturing operations, and also the delivery order to the customer.

In the Gantt chart the current date is marked as a black line, and the due date of the demand is marked as a red line.

Field

Description

Depth

Depth of this operation in the supply path: 0 = delivery, and increases with every level deeper in the bill of distribution and bill of material.

Operation

Operation being planned.

Type

Type of operation with possible values.

  • MO: Manufacturing operation

  • DO: Distribution operation

  • PO: Purchase operation

  • STCK: Inventory

  • DLVR: Delivery to the customer

Item

Item being produced by this operation.

Item description

Description of the produced item.

Resource

Resource(s) being loaded.

Quantity

Quantity allocated to the demand.
In the Gantt chart the operations are shown in detail. Some of the operations may be only partly allocated to the demand being displayed.