Resource report

This report shows the loading of the resources.

If the report is opened for a single resource a load graph is displayed.

The report shows the plan result in size*time. E.g. a resource has size 1 and we are looking at a weekly bucket: available = 7 E.g. a resource has size 3 and we are looking at a weekly bucket: available = 21 The parameter loading_time_units defines the time units. Acceptable values are hours, days and weeks.

Field

Description

Resource

Resource name.

Location

Location of the resource.

Available

Total availability on the resource.

Unavailable

Unavailable time, as defined in the availability calendar of the resource’s location.

Setup

Time spent in conversions between setups.

Load

Time spent on actual manufacturing orders.

Utilization

Equal to the load divided by the available time, expressed as percentage.
The utilization % just right before the graph is the average utilization over the complete reporting horizon. The value for each bucket in that horizon is show in the cells on the right.