Setup Matrices

Resources can require a setup time to change the configuration between different setups/configurations. This models the time required for cleaning, installation of new tooling, re-calibration, feeding new raw materials, etc.

Such changeovers can take an considerable amount of time, and thus have an important impact on the production plan. The production planner will need to group production orders together in batches such to find a balance between reducing the changeover time and extra inventory caused by such grouping.

Example

Excel spreadsheet resource-setup-matrices

This example models a simple painting shop. Products can be painted on 3 equivalent painting lines. When a painting line changes color a setup time is required to clean the machines.

A number of data fields are required for this model:

The generated plan drastically changes as soon as a batching window is specified. The changeovers between operations are shown as a black line. Only a part of the plan is visible in the screenshot.

  • Plan editor without setup optimization
    This plan has many changeovers and a low inventory.
    Plan editor without setup optimization
  • Plan editor with setup optimization and large batching window
    Demand is now produced in very large batches. This results in a minimal changeover cost but large inventory costs.
    Plan editor with setup optimization
  • Plan editor with setup optimization and smaller batching window
    By reducing the batch size window, we obtain a plan that reduces the changeover cost while avoiding excessive inventories.
    Plan editor with setup optimization and small batching window