Operation detail report

The report shows the details of all manufacturing orders. It displays their start date, end date and quantity.

Field Description
Reference Reference of this operation instance.
Operation Name of the operation.
Quantity Quantity of the manufacturing order.
Start date Start date of the manufacturing order.
End date
End date of the manufacturing orders.
Note that in case of unavailable time, the difference between the start and end date can be bigger than the specified duration of the operation. For instance, if the weekends are modelled as unavailable time, an operation with a duration of 1 day can start on friday 7AM and end on monday 7AM.
Feasible
Boolean field indicating whether the manufacturing order is violating any material, lead time or capacity constraints.
This is very handy in interpreting unconstrained plans.
Criticality
Indication of the urgency of the manufacturing order.
A criticality of 0 indicates that the manufacturing order is on the critical path of one or more demands.
Higher criticality values indicate a delay of the manufacturing order will not immediately impact the delivery of any demand.
A criticality of 999 indicates an manufacturing order that isn’t used at all to meet any demand.
Status

Status of the manufacturing order:

  • proposed: newly proposed by the planning tool
  • approved: approved by the planner, but not yet launched in the ERP system
  • confirmed: ongoing transaction, controlled by the ERP system and not changeable in frePPLe
  • closed: operation has finished
Unavailable
Total unavailable time over the duration of the manufacturing order.
Continuing on the above example, the unavailable time would be 2 days.
Owner In case of nested manufacturing order this field shows the identifier of the owning manufacturing order. This applies to operations of type “alternate” and “routing”.
Operation detail report